Infrastructure sequence plans

Information to assist with council awareness and developers

About our infrastructure sequence plans

We've developed infrastructure sequencing plans to be used for:

  • our shared asset budget
  • Council awareness to understand our preferred direction for future growth
  • to give developers a visual understanding of our infrastructure sequencing.

These plans only apply to the towns including future shared assets and are intended as a guide.

The latest infrastructure sequence plans include:

Churchill

  • Area 0e removed as developed.
  • Sequence timing for areas 0 and 1 pushed out one year, sequence timing for area 2 brought forward from 86/87 to 82/83.

Drouin

  • Pump station on Gardner & Holman Rd and Rising Main on Settlement Rd removed these assets have been constructed.
  • Area with sequence timing 4 changed to sequence 3 as shared asset infrastructure constructed (Gardner & Holman Rd Pump Station and Rising Main) 
  • Shared asset sewer gravity main added to area 3j 
  • Shared asset sewer gravity main added to area 3b
  • Sequence timing pushed out 

Heyfield

  • Area 1c reduced to account for flood overlay.
  • Area 1d removed as this area is developed.
  • Sequence timing brought forward from 58/59 to 49/50 for sequence 2 areas.

Maffra

  • No change

Moe-Newborough

  • Sequence timing changed
    • Sequence 2 went from 38/39 to 44/45
    • Sequence 3 went from 79/80 to 80/81
    • Sequence 4 went from 116/117 to 111/112

Morwell

  • Shared asset water main added north of Crinigan Rd 
  • Shared asset sewer gravity main added to Washington Way/Josie Place
  • Sequence timing changed
    • Sequence 2 went from 33/34 to 34/35
    • Sequence 3 went from 66/67 to 65/66

Sale

  • Shared asset water main in area 4a re-aligned to Grassdale Rd
  • Shared asset sewer gravity main extended to the west, through 3a to Grassdale Rd
  • Shared asset water main in 2c updated as per current development progress – Dyer Avenue
  • Sequence timing minor change

Stratford

  • Removal of sequence areas 0 
  • No change to timing

Trafalgar

  • Sequence timing changed 
    • Sequence 2 went from 28/29 to 31/32
    • Sequence 3 went from 32/33 to 35/36

Traralgon

  • Removal of sequence areas 0 as land has been developed
  • Timing of sequence 2 and 3 pushed out a year

Warragul

  • Shared asset Treated Water Pump Station added to 3c area
  • Sequence timing changed 
    • Sequence 2 went from 26/27 to 27/28
    • Sequence 3 went from 30/31 to 32/33 
    • Sequence 4 went from 57/58 to 63/64

Wurruk

  • No change

Yarragon

  • Removal of some sequence areas 0 as land has been developed
  • Sequence timing changed 
    • Sequence 1 went from 24/25 to 25/26
    • Sequence 2 went from 25/26 to 27/28 

 

The establishment of reimbursement rate is set by the signing of the Developer Works Deed. The reimbursement rate is only set and locked at the time of signing. The Deed allows a year for the completion of the works.

If the works are not completed within a year, we may execute a new Developer Works Deed and apply the reimbursement rate at that time.

When developing please contact us for further guidance.